City of Belton

Phase 1 Water System Improvements

Belton, MO

Following Benesch recommendations in City’s updated Water System Master Plan, Benesch was further contracted to design and construct Phase 1 water system improvements. The project addressed current and future water demands for the City over the next 20 years.

The first phase totaled $11 million and included:

  • Design and installation of a new 3.0 MG elevated storage tank
  • 11,700 LF of 16-inch transmission main
  • Rehabilitation work at the existing booster station
  • Rehabilitation work at the existing 300,000-gallon storage tank

In addition, Phase 1 included the following improvements at the existing booster station:

  • New pumps and motors
  • A new motor control center to replace the old and obsolete unit
  • Replacement of a faulty flowmeter

Miscellaneous electrical and mechanical upgrades

Project highlights

  • Storage tank rehabilitation
  • Water main replacement
  • Booster station rehabilitation